Diseño y ejecución de plan de mantenimiento preventivo para el sistema de plantas eléctricas en el terminal de transporte de Neiva s.a.
Nowadays, the Terminal de Transporte de Neiva S.A. is in constant growth, which is why its set of electrical plants is of critical importance, therefore, the company requires a preventive maintenance plan to ensure the supply of electricity in the event of outages that may occur by the energy distri...
Saved in:
Main Author: | |
---|---|
Other Authors: | |
Format: | Trabajo de grado (Pregrado y/o Especialización) |
Language: | spa |
Published: |
Universidad Antonio Nariño
2023
|
Subjects: | |
Online Access: | http://repositorio.uan.edu.co/handle/123456789/8740 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Nowadays, the Terminal de Transporte de Neiva S.A. is in constant growth, which is
why its set of electrical plants is of critical importance, therefore, the company requires a
preventive maintenance plan to ensure the supply of electricity in the event of outages that
may occur by the energy distribution company. Currently, the Terminal de Transporte de
Neiva S.A. has a corrective maintenance plan (when the failure is already present) which
causes unavailability in emergency cases, generating high maintenance costs, economic
lossesfor not being able to perform its activities normally, for not having the necessary spare
parts, since its focus is focused on solving only the failures that are found at that time,
causing low rates of availability and reliability in the set of power plants of the Terminal de
Transporte de Neiva S.A.
This situation has led the company to consider an effective and immediate solution,
for which it is proposed to implement a preventive maintenance plan based on reliability
(RBM), once this preventive maintenance plan is implemented, it will be executed in the set of
power plants installed in the Terminal de Transporte de Neiva S.A. With this implementation
it is expected to increase the availability and reliability rates to 90%, it is also expected that
the student will apply the knowledge acquired during his training as a Mechanical Engineer. |
---|